ABOUT THE PROJECT

R L Burns completed the removal and re-installation, with flashing and sealant modifications, of 65 exterior windows located at the Tampa Executive Airport Terminal Building. This work was performed to correct water intrusion issues. The Work included repair of interior finishes at window locations to correct water damage. Other exterior work included minor repairs to metal panels, installation of new sealants and painting. The interior work included new casework and millwork in the common areas, interior painting, flooring upgrades, refinishing of interior doors, replacement of lighting fixtures, replacement of plumbing fixtures and cleaning of ceramic tile and grout.

DETAILS

Firm’s Responsibility: General Contractor
Project Type: Airport Repair and Maintenance
Client: Hillsborough Aviation Authority
Completion Date: May 2015
Construction Value: $362,300
Key Personnel:
Project Executive: Bob Burns
Project Manager: Jarrett Miller
Lead Foreman: Wayne Walters