ABOUT THE PROJECT

R L Burns was selected as the Design-Builder to renovate the former Comair Hangar for use as Silver Airway’s maintenance hangar and office building.  The scope of work consisted of interior demolition, reconfiguration of office layout, upgrades to interior finished, replacement of hangar doors, construction of new façade with metal wall cladding, upgrades to MEP systems and exterior parking lot lighting upgrades.  Addition scope included the construction of a new 20x20 storage facility.

DETAILS

Firm’s Responsibility: General Contractor
Project Type: Design-Build/Renovation
Client: Greater Orlando Aviation Authority
Completion Date: April 5, 2015
Construction Value: $2,562,203
Key Personnel:
Project Executive: Bob Burns
PreCon Manager: April McIntosh
Estimator: Jarrett Miller